The off-site renewable option in the 2025 NYC Energy Code
Updated · R Solar Solutions
Questions? Call Jack at (646) 535-8762
Serving Brooklyn, Manhattan, Queens, The Bronx, Staten Island, Long Island and Westchester.
How the amount is calculated
The code converts the missing capacity into kilowatt-hours: roughly 1.35 kWh per watt of required capacity per year, multiplied over 15 years, minus whatever the on-site system produces. In plain terms, every kW you can't fit on the roof turns into a long-term purchase obligation.
Why on-site solar usually wins
On-site solar also lowers the building's own electric bills, qualifies for the NYC property tax abatement, and avoids a long contract that a buyer or lender will ask about. Off-site procurement is an ongoing cost with no bill savings on site. Fit as much solar as the roof allows, then buy only the gap.
Common questions
How long must an off-site contract last?
The code requires a long-term contract (at least 10 years) that continues if the building is sold; DOB's guidance references 15 years for some cases. Your energy consultant confirms the term for your path.
Can I just buy RECs?
Buying certified renewable electricity is the last-resort path for buildings that can't meet the on-site or off-site options, and the required amount is larger.
Questions? Call Jack at (646) 535-8762
Serving Brooklyn, Manhattan, Queens, The Bronx, Staten Island, Long Island and Westchester.
Sources: NYC DOB: 2025 NYCECC Chapter C4 (C405.15) · NYC DOB: 2025 NYCECC lighting & power guide
This page is general information, not tax, legal or engineering advice. Incentives change — confirm eligibility with your tax advisor. R Solar Solutions is operated by P National Group LLC, 1 Northside Piers, Brooklyn, NY 11249. Incentive information is general and not tax advice.
Related
The 2025 NYC Energy Code solar requirement (C405.15), explained
New NYC buildings filed from March 30, 2026 need 0.75 W of solar per sq ft of floor area (up to the three largest floors) or off-site renewables. Rules, exceptions and a calculator.
How much solar does a new NYC building need? (sizing table)
Quick sizing for the 2025 NYC Energy Code: 0.75 W per sq ft of the three largest floors. Table of kW, panels and roof area for common NYC floor plates.
NYC Energy Code vs. Local Laws 92/94: which solar rule applies?
Two NYC solar rules apply to new buildings: the 2025 Energy Code sets capacity (0.75 W/sq ft), LL92/94 sets roof coverage. How they differ and how to meet both.
Solar requirements for new multifamily and mixed-use buildings in NYC
New 4+ story apartment and mixed-use buildings in NYC: the 2025 Energy Code solar minimum, LL92/94 roof rules, where the power goes, and how to budget it.
The federal solar tax credit in 2026: what changed
The 30% homeowner credit ended on Dec 31, 2025. Commercial and leased solar can still use Section 48E — if placed in service by Dec 31, 2027. What it means in NYC.
The NYC solar property tax abatement, explained
NYC's solar and storage abatement can cover up to 30% of eligible costs over four years, up to $62,500 a year. How it works, who files it, and who can't use it.