The 2025 NYC Energy Code solar requirement (C405.15), explained
Updated · R Solar Solutions
C405.15 calculator — enter the gross conditioned floor area of the three largest floors.
0.75 W DC per sq ft of the three largest floors (2025 NYCECC C405.15.1). Roof area assumes about 70 sq ft of flat roof per kW. Exceptions and the compliance path are confirmed by your energy consultant.
Questions? Call Jack at (646) 535-8762
Serving Brooklyn, Manhattan, Queens, The Bronx, Staten Island, Long Island and Westchester.
Who it applies to
New buildings designed under the commercial chapter of the 2025 NYCECC with 5,000 sq ft or more of gross conditioned floor area, and additions (for the addition alone). In the energy code, "commercial" includes most buildings other than residential buildings of three stories or less, so most NYC mid-rise multifamily and mixed-use buildings are covered. Projects using the ASHRAE 90.1 path follow that standard's own rules; your energy consultant confirms the path.
It applies on top of Local Laws 92/94, which still require the available roof to be covered with solar, a green roof or both.
How to calculate it
Add the gross conditioned floor area of the three largest floors (or all floors, if fewer than three) and multiply by 0.75 W. Example: three floors of 10,000 sq ft = 30,000 sq ft x 0.75 W = 22.5 kW DC. Use the calculator above for your building.
Exceptions
Buildings with less than 5,000 sq ft of gross conditioned floor area; sites with very low solar resource; buildings where more than 80% of the roof is covered by permanent obstructions; and buildings where more than half the roof is shaded for over 2,500 hours a year between 8 am and 4 pm.
If the roof can't fit it
Buildings that are exempt or can't meet the full on-site capacity must procure off-site renewable energy for the shortfall — through physical or financial power purchase agreements, a community renewable facility, an owner-owned off-site system, a renewable energy investment fund or a green retail tariff — under a long-term contract that survives a sale, with renewable energy certificates retained and retired. Where that isn't possible, the owner must buy certified renewable electricity before occupancy. Off-site paths add ongoing cost, so it usually pays to fit as much solar on the roof as possible.
What goes on the drawings
DOB's guide asks for the system type and capacity, roof plans showing the array and available roof area, shading or obstruction analysis if claiming an exception, inverter and interconnection details, any off-site procurement method and REC documentation, and the compliance calculation. On-site renewables also need separate metering. We prepare the solar side of this package.
Common questions
When did the 2025 NYC Energy Code take effect?
DOB began enforcing it for job filings submitted on or after March 30, 2026. Filings with complete energy submissions before that date may follow the 2020 code; incomplete filings or material compliance changes after that date must follow 2025.
Does a green roof count toward C405.15?
No — C405.15 asks for renewable generation capacity. A green roof still counts for LL92/94 roof coverage.
Do 1–3 story houses need solar under the energy code?
The residential chapter of the 2025 NYCECC does not require on-site solar; LL92/94 can still apply to new buildings and full roof replacements.
Is this legal or engineering advice?
No. It's a summary of the public code text and DOB guidance. Your architect and energy consultant confirm compliance.
Questions? Call Jack at (646) 535-8762
Serving Brooklyn, Manhattan, Queens, The Bronx, Staten Island, Long Island and Westchester.
Sources: NYC DOB: 2025 NYCECC Chapter C4 (C405.15) · NYC DOB: 2025 NYCECC lighting & power guide · NYC DOB: 2025 NYCECC enforcement notice · NYC DOB: 2025 NYCECC Chapter C5 (additions) · NYC DOB: Local Laws 92/94 Solar & Green Roofs
This page is general information, not tax, legal or engineering advice. Incentives change — confirm eligibility with your tax advisor. R Solar Solutions is operated by P National Group LLC, 1 Northside Piers, Brooklyn, NY 11249. Incentive information is general and not tax advice.
Related
How much solar does a new NYC building need? (sizing table)
Quick sizing for the 2025 NYC Energy Code: 0.75 W per sq ft of the three largest floors. Table of kW, panels and roof area for common NYC floor plates.
NYC Energy Code vs. Local Laws 92/94: which solar rule applies?
Two NYC solar rules apply to new buildings: the 2025 Energy Code sets capacity (0.75 W/sq ft), LL92/94 sets roof coverage. How they differ and how to meet both.
Solar requirements for new multifamily and mixed-use buildings in NYC
New 4+ story apartment and mixed-use buildings in NYC: the 2025 Energy Code solar minimum, LL92/94 roof rules, where the power goes, and how to budget it.
Developers and general contractors
NYC developers and GCs: meet the 2025 Energy Code solar rule (0.75 W/sq ft) and Local Law 92/94 with one partner — sized, filed, installed and connected.
Solar for new buildings: 2025 Energy Code + LL92/94
Meet the 2025 Energy Code solar rule (0.75 W/sq ft) and LL92/94 roof coverage — designed, filed, installed and connected.
Solar EPC for developers and general contractors
One subcontract for design, equipment, install and interconnection — built for developers and GCs.